|

Leak Testing With Process Gas
#1
Posted 07 June 2011 - 05:53 AM
I would appreciate any experienced members viewpoint on (1) the safety of doing this and (2) whether it is common practice in the industry to do this (i.e. has it been done in your plant?)
Thanks.
#2
Posted 08 June 2011 - 12:17 AM
As long you removed pieces of equipment you need to do pressure test ?
It's on purpose.
Breizh
#3
Posted 08 June 2011 - 06:56 PM
Always blow down to atmosphere if a leak requires fixing. Do not work on flanges under pressure regardless of the testing medium.
first time poster, just my two cents.
#4
Posted 28 August 2011 - 12:35 PM
It is a normal practice when nitrogen is not available. is it named as service test and is equivalent of leak testing with nitrogen or air. Even if is a high pressure system, is it planned to be hydro tested and fully reinstated, and a derogation to do it with gas is required. As well it is a MUST to have flare system available and in operation (preferable).
A detailed M/S or procedure with a TRA attached is required as well. Pressurisation MUSt be done on steps, 10 to 20 bar increments up to normal operating pressure.
I think now is already done.
Take care
#5
Posted 30 August 2011 - 12:02 PM
1. Hydrostatic (or pneumatic) test occurs with instruments removed from the pipes.
2. After reinstalling the instruments, leakage test occurs with air or nitrogen at a pressure lower than design pressure. If air has been used and the pipe is to transfer a flammable liquid, air is displaced by nitrogen.
3. Using flammable gas in leakage test instead of air or nitrogen was never specifically discussed. But the care of expediting nitrogen unit start up indicated that this was not thought of, apparently due to safety (risk of leakage).
It is pointed out that above has not been applied yet, so they may change a bit. But (mainly for my own knowledge) I would like to ask members to advise / comment on them. I see that leak test is implemented at higher than design pressure (http://www.cheresour...ng-of-a-plant/'> http://www.cheresources.com/invision/topic/12859-software-list-for-commissioning-pre-commissioning-of-a-plant/ and wonder whether a code permits the use of flammable gas as test medium. It seems this is permitted for offsore facilities on sea (see above posts), but what about a refinery build on land? Is above practice too conservative, or represents another practice also used. Hope of some advice.
Edited by kkala, 30 August 2011 - 12:09 PM.
#6
Posted 16 September 2011 - 01:45 PM
Pneumatic testing is carried out for the lines where the supports or structures are not designed for line full of liquid ,normally flare headers.Pneumatic testing is for mechanical integrity check while leak testing is for simple detection of leaks and may not necessarily be carried out at or above design pressure.
As per my experience Being part of a few commissioning teams for high pressure Hydro processing Units ,i have witnessed the following sequence for Leak testing of Reaction Section/HP section.
- Hydro testing About 1.3 times design pressure Multiplied by stress correction factor depending upon design temperature
- Leak testing with Nitrogen in Various Pressure Levels
- Low pressure about 7 kg/cm2 g
- Then about 50% of Design pressure ,with the help of RGC.
- 7 Kg/Cm2 g
- 50% of Design pressure ,with the help of RGC
- Operating pressure ,with the help of RGC
We often detected leaks while testing with Hydrogen that went undetected while testing with nitrogen,because of size of smaller Hydrogen molecule.Whole of the reaction section has to be depressurized to flare and inertized again for attending leaks ,majorly shell side exchanger flanges.
#7
Posted 16 September 2011 - 03:33 PM
#8
Posted 30 October 2011 - 03:56 PM
General Method followed in our Gas processing plant
- After hydro test finished, line has to be air blown to clear any foreign material and it will be leak tested with air initially as most of leak will known by low pressure itself. probably air pressure will be available at 9 bar
- Better prepare small loops which contain same operating pressure of piping/vessel/columns and lineup thro control valve and bypass valve. Do pressure test with air & eliminate the leaks. Try to hold for 12 hrs see the rate of leak.
- Once satisfied, inert the same loop with N2 and eliminate O2 content. Lean sweet Methane gas can be used in the steps of 5 bar until operating pressure of the loop. In my experience you can eliminate most of the leak at minimum pressure itself.
- Rotating equipments can be isolated and & it can be done separately with its design pressure once it connected with process system after flushing the related pipelines.
- If your gas is sour better use higher pressure N2 to avoid hazard conditions as most persons will be new to pant & not familiar with hazard conditions which may lead to human loss.
#9
Posted 10 April 2013 - 11:39 AM
Hello I am a chemical engineer and I have to write a thesis on the leak test oil refinery. So I'm looking for any material that can help me on this topic. Thanks in advance for your contribution
Similar Topics
Psv Backpressure TestingStarted by Guest_sam1111_* , 17 Mar 2025 |
|
![]() |
||
Performance Testing Of Air Cooled Heat Exchanger In Off Design ConditiStarted by Guest_go-fish_* , 09 Dec 2024 |
|
![]() |
||
Going Through The Writing Process.Started by Guest_Haywardvek_* , 05 Jan 2025 |
|
![]() |
||
Typical Process Of Platformate Splitter ?Started by Guest_AnbIran_* , 30 Dec 2024 |
|
![]() |
||
![]() Opportunities For Heat Recovery In A Chemical Process PlantStarted by Guest_tanyongboon1_* , 29 Nov 2024 |
|
![]() |