Hello Folks,
For the current ongoing feasibility study project I have the following issues in calculating the flowrate of Hot water through Jacketed Pipe & Jacketed Vessel:
Jacketed Pipe:
- I have a product which is highly viscous and need to maintain the temperature in the pipe to 52 deg C, below 45 deg C it becomes thicker and the pump is not designed for that viscosity. The product rate is 190 cu.m per hr, density 950 kg/m3, viscosity of 56 cP and thermal conductivity of 0.15 W/(m K). It was recommended to use Hot water jacketing around the pipe and maintain the temp to 52 C. The hot water is available at 65 deg C. The product pipe size is 200 NB
- Approach 1: If I assume that the temp drop across the product is 1 deg C then I need to heat the product from 51 C to 52 C using hot water which has a delta T of 10 C and hence by simple heat balance across the product and the water gives me :
Mass of water (kg/hr) = 190*950*1.91*(52-51)/(4.18*(65-55)) = 8,248 kg/hr = 8.24 cu m per hr
But this seems to be on a very much higher side. Am I correct??
- Approach 2: If I insulate the product pipe with rookwool, and using insulation thickness calculation method I arrive at a figure of 50 mm thickness, with a heat loss to the surrounding as 37.2 W/m of pipe. Surrounding atmosphere conditions Air at 0 deg C and velocity of 5 m/s.
And if consider zero thickness the heat loss to surrounding as 600 W/m of pipe. If then I use water to circulate around to absorb this much heat loss then the water required is 52 kg/hr.
Kindly advise which approach shall I follow in order to calculate the water required in jacketed pipe.
Jacketed Vessel:
- I have a product which is highly viscous and need to maintain the temperature in 3 batch storage vessel, the vessel dia is 5 m and height is 10 m and volume is 200 cu.m each.
The required temp to be maintained in the vessel is 52 deg C, below 45 deg C it becomes thicker and the pump is not designed for that viscosity. Density 950 kg/m3, visocisity of 56 cP and thermal conductivity of 0.15 W/(m K). It was recommended to use Hot water jacketing around the vessel and maintain the temp to 52 C. The hot water is available at 65 deg C.
Kindly advise how to calculate the Hot water rate. There is no product rate as its a batch process the volume of the vessel is apprx the mass of the product.
Regards
Pratik