In an Engg. Procurement and Construction (EPC) project for the creation of a process plant, when is process simulation done? I mean whether it is done by Process Licensor or EPC contractor?
| 
 | 
  
			
				
					
						
					
					#1
					
					
				
				
				
					
				
			
				
			
			
			Posted 22 March 2015 - 11:10 PM
			
				
					
						
					
					#2
					
					
				
				
				
					
				
			
				
			
			
			Posted 31 March 2015 - 07:17 AM
The simulation will often be done at each stage: Conceptual, FEED and EPC. It is in the best interest of all parties - the licensor, the EPC contractor and the owner to have a simulation of the project.
Most often, the simulation moves with the project. It is created in conceptual phase, modified in FEED and again in EPC. All the while, if the the owner of the plant is doing their due diligence, they will have the updated models at the end of each phase as a way to check the engineering companies.
The licensor should give the EPC at least a H&M balance for their portion of the work (I would ask for the model), which most often is enough for the EPC contractor or the owner to build a model.
All these details should be worked out at the beginning of the project and made clear to all parties.
Similar Topics
		
		
		
		
		
		
		
		Mastered Process EngineeringStarted by Guest_Boudinahh8777_* , 31 Oct 2025  | 
	
	
		
  | 
	
		
	 
	 | 
	
||
		
		
		
		
		
		
		 Seeking Feedback On My Process Flow Diagram. Biogas Steam Reforming ToStarted by Guest_Jacobaum_* , 27 Oct 2025  | 
	
	
		
  | 
	
		
	 
	 | 
	
||
		
			Sizing And And Process Control Of Filter PressStarted by Guest_Amalina Jamil_* , 11 Mar 2019  | 
	
	
		
  | 
	
		
	 
	 | 
	
||
		
		
		
		
		
		
		 Any Ways Or Where To Find The Licensor Process?Started by Guest_adrianong_* , 19 Sep 2025  | 
	
	
		
  | 
	
		
	 
	 | 
	
||
		
		
		
		
		
		
		
		Static Simulation Of An Atmospheric CduStarted by Guest_tomr91_* , 10 Aug 2025  | 
	
	
		
  | 
	
		
	 
	 | 
	

   FB





	