I’m a member of the Commissioning team working on our greenfield refinery project. We have steam pipelines with a minimum length of 10 KM and a maximum length of 20 KM, including laterals for consumers. Before steam blowing activity, do we need to perform rotomol cleaning? Additionally, due to the pipeline’s long length, there are numerous drip legs. What are the chances of these drip legs getting clogged with dust, rust, or scale? Is there a method to reduce the issue of dislodged scale and minimize the time required for steam header commissioning?
|


1 reply to this topic
Share this topic:
#1
Posted 24 February 2025 - 06:32 AM
#2
Posted 24 February 2025 - 06:46 AM
Hi,
You may find pointers in the link attached:
https://www.transcen...mical-cleaning/
Should have been investigated during the project and costs allocated.
At minimum steam blowing. Duration depends on the cleanliness of the pipe.
Good luck
Breizh
Similar Topics
Steam Pressure In Heat ExchangerStarted by Guest_mvanrijnbach_* , 15 Apr 2025 |
|
![]() |
||
Heat Exchanger Steam FlowStarted by Guest_aliebrahem17_* , 25 Nov 2024 |
|
![]() |
||
![]() Steam Carrying Liquid From The Sour Water Stripping TowerStarted by Guest_kaidlut_* , 12 Sep 2024 |
|
![]() |
||
Converting Superheated Steam To Saturated SteamStarted by Guest_addiesalsabil_* , 10 Sep 2023 |
|
![]() |
||
Steam Methane Reforming Mass BalanceStarted by Guest_buskivi_* , 05 Jan 2025 |
|
![]() |